Nashville Airport Signs 40-Year Tunnel Deal With The Boring Company
MNAA signed a 40-year license with The Boring Company on Nov. 18: $300,000 annually rising 3%, $5 per passenger movement, no airport capital. Launch targeted for early 2027.
Read-back
- MNAA and The Boring Company signed a 40-year licensing agreement on Nov. 18
- Annual fee starts at $300,000, rising 3% yearly, plus $5 per airport passenger pickup or drop-off
- The Boring Company covers all construction, operations and maintenance costs and reimburses $600,000 in negotiation expenses
- Two tunnel-boring machines are active under downtown Nashville; a third is being prepared
- Company targets an early 2027 launch, but no definitive opening date is set

Nashville International Airport has committed no capital to a 40-year tunnel project, and it will still collect rent. The Metropolitan Nashville Airport Authority (MNAA) and The Boring Company signed a licensing agreement on Nov. 18 covering an underground transportation system linking BNA with downtown Nashville.
The project, called the Music City Loop, will use twin one-way tunnels and a fleet of electric vehicles carrying passengers between the airport and stations across the city. MNAA frames the system as a tool to relieve roadway congestion as passenger traffic grows.
What does the agreement actually cost the airport?
Nothing up front. The Boring Company assumes all construction, operations and maintenance costs. The financial terms run in one direction, mostly toward the airport authority:
- An annual licensing fee starting at $300,000, escalating 3% each year
- A $5 fee per passenger pickup or drop-off at the airport
- Reimbursement of $600,000 in MNAA's negotiation expenses
For a public authority, that structure is unusual. The airport diversifies ground transportation and builds a new revenue stream without writing a check. The trade-off is control: for four decades, a private company will operate a core passenger access function on airport land.
What changes at the terminal?
The plans specify tunnel portals behind Concourse D and an extension of an existing service road. The Boring Company will lease a 19,500-square-foot covered pickup and drop-off area, currently used by taxis and limousines. That lease converts an existing curbside function into the loop's airport station footprint.
The detail matters operationally. Taxis and limousines lose covered space to a system that has not yet opened. The agreement does not state where those operators move, and the source is silent on replacement facilities.
Is the 2027 date real?
The company targets an early 2027 launch. No definitive opening date exists. Two tunnel-boring machines are working beneath downtown Nashville, and a third is being prepared for deployment. Machines in the ground are verifiable progress; a launch target is not.
The Boring Company's schedule claims deserve scrutiny. The machines are boring downtown, not at the airport, where portals behind Concourse D remain plans on paper. A system connecting both ends requires both segments finished, tested and certified for passenger service. The source offers no construction milestones between now and 2027.
What is the financial upside for MNAA?
The licensing arithmetic is modest at first. At $300,000 in year one with 3% annual escalation, the base fee reaches roughly $723,000 by year 20. The per-passenger fee scales with volume, but MNAA has published no ridership projections that would let anyone model it. If the loop carries two million airport passengers a year, pickups and drop-offs yield several million dollars annually; at 500,000, far less. Without traffic forecasts, the revenue claim cannot be tested.
The agreement's real value to the airport is strategic rather than immediate. Ground congestion at BNA grows with passenger volumes, and curb space is finite. A below-grade alternative adds capacity without land acquisition or capital outlay.
What remains unverified?
Three claims warrant watching. First, the 2027 launch has no committed date. Second, the per-passenger revenue model has no published ridership basis. Third, the passenger experience — fleet size, vehicle capacity, headways, fares — goes undescribed in the agreement's public summary.
The 40-year term also outlasts several technology cycles. What electric vehicle fleets look like in 2065 is anyone's guess, and the agreement's renewal or exit terms are not disclosed.
For now, the hard facts stand: a signed 40-year license, $300,000 a year rising 3%, $5 per passenger movement, $600,000 in reimbursed expenses, and two boring machines already working. Everything else — including early 2027 — is a target the company must still meet.
via Aviation Pros (Source)
More from James Calloway
Show full bio
Staff writer covering people, launches and day-to-day practice in Commercial aviation industry coverage at Flightdeck Report.
726 articles
Same bay
- MWAA Awards Jacobs and TYLin $150 Million Program Management Deals · November 19, 2026
- Jackson Airport Board Advances Private-Sector Terminal Plan at JAN · November 13, 2026
- FAA channels $84.4 million in AIP grants to four airports across three states · October 10, 2026
- Memphis Airport Board Approves $98.7 Million Terminal Contract · November 19, 2026
- Charlotte Approves Airline Lease Unblocking $2.1 Billion Airport Expansion · November 13, 2026