Long Thanh Airport at 86% Complete Ahead of December 24 Opening
Long Thanh International Airport stands at 86 percent completion ahead of a December 24 first flight, opening with 226 weekly flights under Vietnam Airlines' initial network.
Read-back
- Long Thanh International Airport is 86% complete, with first commercial flight set for December 24.
- ACV estimates 226 flights per week from December 2026 to March 27, 2027 — 182 domestic, 44 international.
- Total investment exceeds VND336.63 trillion (US$13 billion) across 5,000 hectares.
- Vietnam Airlines has registered 44 weekly international flights to Beijing, Guangzhou, Hong Kong and Manila, plus 28 weekly to Ha Noi.
- Full build-out targets 100 million passengers and 5 million tonnes of cargo annually.

Long Thanh International Airport is 86 percent complete, with its first commercial flight scheduled for December 24, according to Airports Corporation of Viet Nam (ACV).
Check-in counters, baggage carousels and seating inside the lotus-shaped terminal in Dong Nai province, southern Vietnam, are now being fitted out. Most construction packages should finish in December, ACV said. The corporation did not say which packages remain unfinished or what contingency exists if they slip past the opening date.
What capacity does the airport open with?
The figure is modest. Based on slot allocations from the Civil Aviation Authority of Viet Nam and airlines' operating plans, ACV estimates a maximum of 226 flights per week between December 2026 and March 27, 2027. Of those, 44 are international services and 182 are domestic.
That number matters because it is a long way from the airport's design ambition. Long Thanh covers roughly 5,000 hectares with total estimated investment of more than VND336.63 trillion, about US$13 billion. Once fully completed, the site is designed to handle up to 100 million passengers and five million metric tons of cargo annually. Nothing in the source indicates when that full capacity will be reached, and the gap between 226 weekly flights and 100 million passengers is the story ACV's announcement leaves unanswered.
Which airlines have committed?
Vietnam Airlines is the anchor operator, and its filings define the opening network.
- International: Beijing, Guangzhou, Hong Kong and Manila, totaling 44 flights per week.
- Domestic: 28 weekly flights on the Long Thanh–Ha Noi route.
No other carrier appears in the slot data cited by ACV. Whether VietJet or foreign airlines follow, and when, is not stated.
Why Vietnam is building it
Construction began in 2020. The first phase comprises four component projects. The airport's stated purpose is to relieve pressure on Ho Chi Minh City-area capacity and anchor a southern hub, though the source does not detail the phasing schedule beyond phase one or the funding breakdown across the VND336.63 trillion program.
What does this change for passengers and carriers? In the near term, little: the December 24 opening adds a modest schedule concentrated on Vietnam Airlines' trunk routes to Ha Noi and four North Asian gateways. The strategic weight rests on later phases, and on execution that ACV's 86 percent figure does not yet prove.
The December construction deadline is tight. Most packages are "expected" to close in the same month as the first flight, which leaves little margin between handover and commercial service — a schedule risk ACV has not addressed publicly.
via en.baochinhphu.vn (Source)
More from James Calloway
Show full bio
Staff writer covering people, launches and day-to-day practice in Commercial aviation industry coverage at Flightdeck Report.
726 articles
Same bay
- Long Thanh airport to open on 24 December 2026 at 366 weekly flights · November 2, 2026
- Long Thanh Airport Sets December 2026 Opening With 366 Weekly Flights · November 8, 2026
- Phu Quoc expansion on track for April 2027 opening · October 2, 2026
- Vietnam's PM asks Airbus to study MRO centers at two new airports · November 6, 2026
- Emirates puts A350 on all four daily Vietnam flights by December · October 29, 2026