Sacramento International Closes Terminal B Roads for Walkway Work

Sacramento International is detouring Terminal B traffic through late October as a $140 million walkway replaces the people mover, part of a $1.38 billion capital program.

Read-back

  1. Terminal B arrivals road serving Doors 1 and 2 closed 1-9 a.m. daily through Oct. 1; detours route drivers to Doors 3 and 4.
  2. A $140 million, quarter-mile walkway with moving sidewalks and escalators will replace the existing automated people mover; the airport targets a year-end opening.
  3. The work sits within SMForward, an estimated $1.38 billion, four-year program that includes a 5,537-space parking garage opening in November and rental car facility relocation construction starting in 2027.

Sacramento International Airport will shut the road serving two of Terminal B's four arrivals doors through October 1, as construction advances on a roughly $140 million pedestrian walkway that will replace the terminal's automated people mover.

The arrivals-side closure affects Doors 1 and 2 between 1 a.m. and 9 a.m. daily. Drivers will be detoured to Doors 3 and 4 on the opposite side of the terminal, the airport said in a news release. A second phase follows from October 15 to October 28, when the Terminal B departures road closes nightly from 8 p.m. to 3 a.m., with posted detour signage.

The disruption stems from construction of the approximately quarter-mile walkway between the check-in area and Terminal B's gates. The facility will feature moving sidewalks, escalators and a central hub designed so the airport can eventually add a third concourse at that location.

The Sacramento County Department of Airports has set a goal of opening the walkway by the end of the year, an airport spokesperson said in June.

The walkway forms one component of SMForward, a four-year capital program the airport values at an estimated $1.38 billion. The program also includes a new 5,537-space parking garage scheduled to open in November and the relocation of rental car facilities, with that construction set to begin in 2027.

For passengers, the near-term effect is limited to ground traffic. The arrivals closure concentrates pickup activity at Doors 3 and 4 during the overnight and morning window, while the October departures closures fall outside most peak departure banks. Airlines operating from Terminal B — the facility's larger of two terminals — face no announced impact on curbside check-in beyond the nightly detours.

The walkway replacement marks a structural shift in how the airport moves passengers airside. The existing automated people mover, one of the defining features of the airport since Terminal B opened, will give way to a conventional walking connection with mechanized assistance. That design choice reduces reliance on fixed-rail transit technology and its maintenance burden, while the central hub layout preserves expansion capacity for a future third concourse if passenger growth justifies it.

The sequencing is deliberate: the garage opens in November, the walkway is targeted for year-end, and rental car relocation construction begins in 2027. Together the projects address the three main friction points at a mid-sized California airport — parking supply, airside circulation and landside rental car traffic — under a single funding envelope.

Whether the walkway meets the end-of-year target will become clear as the October closures conclude. If the schedule holds, passengers arriving for the holiday travel period will use the new connection for the first time.

via facebook.com (Original)

Filed under

  • sacramento-international-airport
  • terminal-construction
  • passenger-walkway
  • smforward
  • airport-infrastructure
Share this article:

More from Priya Raman

Priya Raman

Show full bio

Market editor covering business strategy at Flightdeck Report.

175 articles

Same bay

« Previous articleNext article »